Skip to main content
close
Font size options
Increase or decrease the font size for this website by clicking on the 'A's.
Contrast options
Choose a color combination to give the most comfortable contrast.
  • Denmark Parking Entrance
  • Denmark Front Entrance
  • January Montage Slider 3 wide
  • February Montage Slider 3 wide
leftright

Denmark Library Overview

Designed by McMillan Pazdan Smith Architecture, the 22,504 square foot building will feature nature-inspired design elements to complement the panoramic views of the 9.5 acre lot. Construction is expected to be completed in late 2024 or early 2025 by Albion General Contractors, Inc.

Construction Progress

This time-lapse video captured by Albion General Contractors, Inc. shows the construction progress of the Denmark Library from August 2023 to March 2024.

Special Features of the Denmark Library Design

    • Denmark Library will be the first library in the county with a drive-up window for retrieving holds. This is intended to provide maximum convenience and accessibility for patrons.
    • Denmark will have more study rooms (6) than any other library in Forsyth County.
    • Denmark Library will have a partitionable 2,611 square foot meeting room that can be used for library programs or reserved by the public.
    • Denmark will feature 75,000 books and materials in a variety of languages tailored to the residents of Forsyth County.
    • Denmark Library will include a 412 square foot quiet room that is perfect for reading or studying.
    • Denmark will be the first library in the county to offer smaller study rooms designed for 1–2 people, perfect for remote personal working spaces.

Denmark Library Location

530 Fowler Road, Alpharetta, GA 30004

Map showing the FCPL branches location

Existing FCPL Locations
Denmark Library Site


Denmark Library Floor Plan

Denmark Library floor plan rendering using different colors to highlight areas

Denmark Library Project Updates

    • This month, crews have completed the installation of the roof decking and are 90% finished with the exterior wall framing. The first binder layer of asphalt has been laid on all driving and parking surfaces and all sidewalks are complete. Over the next few weeks, we expect the installation of exterior walls to begin, along with the framing for storefront glass windows and the addition of roofing insulation.

    • During the first part of March, construction teams added roof decking which is now 60% complete. Once roof decking is finished, crews will begin installing the building’s perimeter wall. We also expect the addition of asphalt in April when the temperatures are more moderate. The construction site also got a visit from our future Denmark Library Branch Manager Sarah Reynolds guided by IT and Facilities Manager Holly Barfield!

      It has been a soggy spring so far, but despite the rain, crews have completely finished placing and securing the roof decking. The installation of perimeter walls and framing has begun. Curbing and gutters have been added to the front of the building and pickup window areas and we expect completion soon, depending on weather conditions.

    • The main building’s frame is now completed and roof decking is currently being placed. The interior ceiling shown in the photos is made of acoustical panels which will serve as the finished ceiling for the majority of patron areas throughout the Library. A turn lane is being cut in from Fowler Road, and curbing and gutter leading from the main road has been poured, giving the entryway a more defined look. Over the coming weeks, the focus will be on completing the roof decking and beginning the installation of the perimeter wall framing.


      This time-lapse video captured by Albion General Contractors, Inc. shows the construction progress of the Denmark Library from August 2023 to February 2024.

    • Construction on the building has begun, with vertical steel supports and I-beams being installed. The Library loading dock's final cement pour was also completed. In the coming weeks, the main focus will be on erecting steel and putting on the steel decking for the roof.

    • In early December, crews worked on the parking lot by laying gravel, installing curbing and completing the initial asphalt layer.

      Later in December, concrete was poured in the early morning hours to complete the building pad and ensure maximum drying time.

    • Crews continued work on the storm drainage system and access vault. They also completed the building's footings and added parking lot curbs and gutters.

    • The team carried out proof rolling and impaction testing to ensure stability for the building pad and worked to get the storm drainage system installed.

    • The grading of the building pad is now finished and we are turning our attention to the grading of the parking lot and preparing the site for the storm drain, sanitary sewer, and underground utilities.

    • We officially broke ground on the Denmark Library on July 27, 2023 and are now actively preparing the site for construction. The initial erosion control requirement and inspections have been completed. Up next: grading, storm drainage, and utilities!

    • The Library hosts a groundbreaking for the Denmark Public Library on Thursday, July 27, 2023 including Library Board members along with other county officials.

    • The Library signs contract with Albion General Contractors.

    • The Library selects McMillan Pazdan Smith as the architect.

Denmark Library Funding Sources

Denmark Library Funding illustrated with a pie chart

Our Partners